计日工
- 与 计日工 相关的网络例句 [注:此内容来源于网络,仅供参考]
-
If a Daywork Schedule is not included in the Contract, this Sub-Clause shall not apply.
如果合同中没有计日工报表,则本款不适用。
-
The work shall then be valued in accordance with the Daywork Schedule included in the Contract, and the following procedure shall apply.
对于此类工作应按合同中包括的计日工报表中的规定进行估价,并采用下述程序。
-
The work shall then be value d in accordance with the Daywork Schedule included in the Contract, and the following procedure shall apply.
对于此类工作应按合同中包括的计日工报表中的规定进行估价,并采用下述程序。
-
The Contractor shall then be paid for such varied work under the terms set out in the daywork schedule included in the Contract and at the rates and prices affixed thereto be him in the Tender.
对这类工作应按合同中包括的计日工明细表中规定的项目及承包人在其投标书中对此所定的单价和价格支付承包人费用。
-
Except for any items for which the Daywork Schedule specifies that payment is not due, the Contractor shall deliver each day to the Engineer accurate statements in duplicate which shall include the following details of the resources used in executing the previous day's work
除了计日工报表中规定的不进行支付的任何项目以外,承包商应每日向工程师提交包括下列在实施前一日工作时使用的资源的详细情况在内的准确报表,一式两份
-
Variations 52.3 Exceeding 15 Percent If, on the issue of the Taking-Over Certificate for the whole of the Works, it is found that as a result of: all varied work valued under Sub-Clause 52.1 and 52.2, and all adjustments upon measurement of the estimated quantities set out in the Bill of Quantities, excluding Provisional Sums, daywork and adjustments of price made under Clause 70, But not from any other cause, there have been additions to or deductions from the Contract Price which taken together are in excess of 15 per cent of the "Effective Contract Price"(which for the purposes of this Sub-Clause shall mean the Contract Price excluding Provisional Sums, and allowance for dayworks, if any) then and in such event (subject to Any action already taken under any other Sub-Clause of this Clause), after due consultation by the Engineer with the Employer and the Contractor, there shall be added to or deducted from the Contract Price such further further sum as may be agreed between the Contractor and the Engineer or, failing agreement, determined by the Engineer having regard to the Contractor's Site and general overhead costs of the Contract.
如果在签发整个工程接收证书时,发现由于: 47 超过百分之 52.3 十五(15%)的变更所有按第52.1款和52.2款规定作价的全部变更工程;对工程量清单中开列的估算数量进行计量所做的全部调整费用,但不包括所有暂定金额,计日工作费用及按本文第 70 条规定所作的价格调整。而并非由于任何其他原因,当加到或从合同价中减去的金额总和超过了有效合同价格就本款而言,应指不包括暂定金额和计日工(如有的话的合同价的 15%时,那么,工程师应在与承包人和业主协商后,在考虑据本款采取的任何步骤后,再将合同价减少或增加一笔工程师与承包人协商的调整金额,若不能达成一致意见,则由工程师考虑承包人的现场管理费用及总管理费开文后确定此数额。
-
At end of each mouth the Contractor shall deliver to the Engineer a priced statement of the labour, materials and the Contractor's Equipment, except as aforesaid, used and the Contractor shall be not entitled to any payment unless such lists and statements have been fully and punctually rendered. Provided always that if the Engineer considers that for any reason the sending of such lists or statements by the Contractor, in accordance with the foregoing provision, was impracticable he shall nevertheless be entitled to authorize payment for such work, either as daywork, on being satisfied as to the time employed and the labour, materials and Contractor's Equipment used on such work, or at such value therefore as shall, in his opinion, be fair and reasonable.
每个月末,承包人应向工程师送交一份不包括上段内容的所用劳务,材料,承包人的机械设备并标有价格的结帐清单,如承包人未能将此结帐单与报表开列齐全,准时提交,则承包人无权获得任何款项,但是如工程师认为按上述规定,承包人的清单和结帐单的呈报由于任何原因而实际无法做到,则工程师仍然有权核准此等工作款项,该项款项或按计日工计算(工程师必须对该工程所雇的劳力,时间,所用的材料和承包人的设备情况表示满意)或按工程师认为公平合理的该项工程的价值计算。
-
Acceptance Criteria Activity Duration Estimation; Activity Definition; Activity Sequencing; Addenda Approved budget Arbitration Award of Contract ; Award Criteria Audits Balanced Matrix; Baseline Bill of Quantities Brainstorming Characteristic Checklists civil engineering civil building Claims Clarify Closing Communication Management Communications Planning Communications Skills Communication channels or paths Completion Computer-based Concrete structure Conditions of Contract Conflict Management Contract Management Contract administration Change Control Contract Closure Contract file Contract agreement; Contractual obligations Contractor Contractor's Representative Construction Management Planning Contract Price Control Chart Cost Estimating; Cost of Quality Cost Control Cost Budgeting Cost Management Co-operation Failure costs Critical Path Feedback Fixed-price Fossils Force Majeure Daywork Functional Organization Decision; Fundamental Tenets Decision Tree Defects Liability Definitions Delphi technique General Rules Deliverables General Provisions Deviation; Generation Direct Costs Discounted cash flow; Dissemination Highway engineering; Discharge Human Resource Management; Disputes Human Resource Planning Drawings Hydraulic engineering; Hydroelectric engineering; Employer's Taking Over Identity Certificate Evaluation of Tenders Initiating Process Group; Executing Process Group Instructions to Tenderers Industrial building Investment payback analysis; Ineffective Individual and team performance Information Distribution Negotiation Indirect Costs Nominated Subcontractors Incentive bonus Information Technology Interpretation; Insurance Observation Inspections Off-site Online On-the-job training Opening of Tender
验收标准活动时间的估计;活动的定义;活动序列分析;增编核定预算仲裁授予合同;授标标准审计平衡矩阵;基线工程量清单集思广益特性清单土木工程民用建筑索赔澄清闭幕通信管理通信规划沟通技巧沟通渠道或路径完成以计算机为基础的混凝土结构合同条件冲突管理合同管理合同管理变更控制合同结束合同文件合同协议;合同义务承包承包商的代表规划建设管理合同价格控制图成本估算;质量成本成本控制成本预算成本管理合作失败成本关键路径反馈固定价格化石不可抗力计日工职能组织决定;基本原理决策树缺陷责任定义德尔福技术的一般规则交付的一般规定偏差;代直接费用贴现现金流量;传播公路工程;放电的人力资源管理;争端的人力资源规划图纸水利工程;水电工程;雇主接管身份证书评标启动过程组;执行过程组指示的投标工业建设投资回报分析;无效个人和团队的业绩信息分配谈判指定分包商的间接费用激励奖金信息技术解释;保险观察视察场外在线在职培训开幕投标
- 推荐网络例句
-
They weren't aggressive, but I yelled and threw a rock in their direction to get them off the trail and away from me, just in case.
他们没有侵略性,但我大喊,并在他们的方向扔石头让他们过的线索,远离我,以防万一。
-
In slot 2 in your bag put wrapping paper, quantity does not matter in this case.
在你的书包里槽2把包装纸、数量无关紧要。
-
Store this product in a sealed, lightproof, dry and cool place.
密封,遮光,置阴凉干燥处。