英语人>网络例句>桥墩 相关的搜索结果
网络例句

桥墩

与 桥墩 相关的网络例句 [注:此内容来源于网络,仅供参考]

The main method of reinforcement pier is use different materials in the external of damaged pier, but in most of case, the damaged pier cant be repaired in time, so in this paper, we can solute such questions through architectonics so that the bridge pier capacity can keep from loss largely.

现有的加固方法主要是利用不同的材料在外部对损伤的桥墩进行加固,但是在很多情况下,桥墩不能够及时进行加固处理,所以本文通过构造性的设计方案,来解决在不能及时加固情况下,桥墩承载力不至于有较大的损失。

When train running on the track, there has interaction between whiles and track, and the track will bend because of the weight of wheel. The bend wave will propagate to box-beam and further to bridge pier. Then the vibration propagate to around soil through the bridge pier, which can cause the second vibration on buildings.

列车运行时,车轮和轨道间存在着相互作用,由于轮重的作用使轨道产生弯曲变形,弯曲波通过轨道垫块传给箱型梁,进一步传递给桥墩,然后振动通过桥墩向周围土中传播,从而进一步引发建筑物的二次振动。

In order to solve the composite inversion problem of the flexible arm structure, an improved identification method is proposed by combining the relaxation method with the modified total compensation method.

为了解决悬臂型桥墩结构在输入信息未知条件下的物理参数识别问题,采用将松弛法与改进的全量补偿算法结合起来的算法,通过对参数的离散化,对输入未知条件下的-悬臂型桥墩结构的多个物理参数进行了识别。

Furthermore, buckling effect factors and their influence law are exploited. Finally, combining the character of piles foundation with high bridge piers with engineering practice, four optimal mathematic models are proposed and flow diagram of optimization analysis is fulfilled by the computer optimum program. A numerical example is analyzed to get optimal solution by using this program. Meanwhile based on the optimal model with buckling coefficient as the objective function, parameter variables are discussed about their effect rule toward the optimal value of objective function.

最后,针对高桥墩桩基础的特点,在基本优化模型的基础上,根据不同的目标函数建立了相应的优化模型,给出优化设计算法流程图,编制了相应的优化计算程序;并根据高桥墩桩基的工程实际设计了一个数值算例,采用本文编制的优化计算程序对该结构进行优化,得到了优化后的最优解;同时,采用高桥墩桩基屈曲系数作为目标函数的优化模型进行因素分析,初步探讨了参数变量对目标函数最优值的影响规律和程度。

The invention has the advantages that by means of single film growth craft, supporting structures of a pier, a bridge leg, and a deck are accomplished, thus greatly lowering the difficulty and complicity of the craft; the pier, the bridge leg, and the deck are formed into a trinity, thus assuring the mechanical support of the whole micro bridge to be firmer and to have higher stability; meanwhile, the pier manufactured by means of the single film growth craft has a hollow shape, thus ensuring that the manufacturing process of the electrical channel of the micro-bridge structure is more simple, without the need of tapping in the pier; only simple photoetching craft is needed to guarantee the connection between the electrode at the upper end and the electrode at the lower end.

本发明利用一次薄膜生长工艺完成桥墩、桥腿和桥面的支撑结构,大大降低了工艺难度和复杂性,且桥墩、桥腿和桥面三位一体,使得整个微桥的机械支撑更为牢固,稳定性更高;同时,本发明利用一次薄膜生长工艺制作出的桥墩成空心状,使得微桥结构的电学通道制作过程变得更为简单,无需另外在桥墩中开孔,只需简单的光刻工艺即可保证上端电极和下端电极相连。

Based on the model, a program is put forward in microcomputer, which is achieved by the substructural model synthesis method.

在算法上,采用了节省内存,计算效率高的动态子结构模态综合法,实现了本文提出的桥墩空间动力分析模型的微机计算,为桥墩振动分析、地震力估算与病害桥墩的状态模拟提供了基础。

The superstructure uses the standard drawing, the substructure has used the gravity T-shape abutment and the rectangular buttress, in the design carries on the size to the abutment and the bridge pier to draw up, simultaneously satisfies the design the principle, the abutment uses 9.3m, in satisfies the structure and under the operation requirements premise, the abutment uses 9.3m to be long, because the geological condition decided, the pillar body uses 12m to be high, the open excavation foundation, the process load computation and the load combination, has carried on the bridge abutment and the pillar bottom section stress separately to the abutment and the bridge pier examines calculated, examines calculated the result conforms to the standard requirement, the bridge span uses the straight line build, and established this bridge construction organization plan, including the engineering project characteristic, the construction plan, the job practice, the bridge building construction technology, the measure has drawn up the top cap and the tray structure and matches the muscle chart, finally has drawn up Shui Xigou the bridge overall and the horizontal plan.

上部结构采用标准图,下部结构采用了重力式T 形桥台和矩形桥墩,设计中对桥台和桥墩进行了尺寸拟定,在满足构造和使用要求的前提下,桥台采用9.3m长,由于地质条件决定,墩身采用12m高,明挖基础,经过荷载计算和荷载组合,对桥台和桥墩分别进行了台底和墩底截面应力的检算,检算结果符合规范要求,桥跨采用直线布设,并且编制了该桥的施工组织设计,其中有工程项目的特征、施工方案、施工方法、桥梁工程施工技术,措施绘制了顶帽及托盘构造及配筋图,最后绘制了水溪沟大桥的总体及平面图。

The superstructure uses the standard drawing, the substructure has used the gravity T-shape abutment and the rectangular buttress, in the design carries on the size to the abutment and the bridge pier to draw up, simultaneously satisfies the design the principle, the abutment uses 9.3m, in satisfies the structure and under the operation requirements premise, the abutment uses 9.3m to be long, because the geological condition decided, the pillar body uses 12m to be high, the open excavation foundation, the process load computation and the load combination, has carried on the bridge abutment and the pillar bottom section stress separately to the abutment and the bridge pier examines calculated, examines calculated the result conforms to the standard requirement, the bridge span uses the straight line build, and established this bridge construction organization plan, including the engineering project characteristic, the construction plan, the job practice, the bridge building construction technology, the measure has drawn up the top cap and the tray structure and matches the muscle chart, finally has drawn up Shui Xigou the bridge overall and the horizontal plan.

内昆铁路水溪沟大桥,中心里程为DK608+393.00,该桥的设计方案有三个,通过技术、经济比较,采用4×32m预应力混凝土简支梁桥方案,桥梁全长149.5m,I级单线铁路,设计时速为120km/h,设计荷载为中活载。上部结构采用标准图,下部结构采用了重力式T 形桥台和矩形桥墩,设计中对桥台和桥墩进行了尺寸拟定,在满足构造和使用要求的前提下,桥台采用9.3m长,由于地质条件决定,墩身采用12m高,明挖基础,经过荷载计算和荷载组合,对桥台和桥墩分别进行了台底和墩底截面应力的检算,检算结果符合规范要求,桥跨采用直线布设,并且编制了该桥的施工组织设计,其中有工程项目的特征、施工方案、施工方法、桥梁工程施工技术,措施绘制了顶帽及托盘构造及配筋图,最后绘制了水溪沟大桥的总体及平面图。

In order to study local scouring field near the pier with sediment control dam ,the 3-D velocity field of the pier in monomer model is subtly measured by ADV velocimeter of Sontek.

采用Sontek公司声学多普勒测速仪对有拦沙坝防护的模型桥墩附近流场进行了精细测量,对桥墩冲刷坑内三维流速分布进行了分析,给出了冲刷坑内三维紊动特征量的分布,分析研究了有拦沙防护坝时桥墩局部冲刷的三个新特点,提出了拦沙坝的适用条件。

In order to study local scouring field near the pier with sediment control dam, the 3-D velocity field of the pier in monomer model is subtly measured by ADV velocimeter of Sontek. This paper analyses the velocity distribution in the scouring pool of pier and takes turbulent strength distribution in different direction. Three new characters for the local scours of piers with the sediment control dam are analyzed and the dam's applicability is brought forward.

采用Sontek公司声学多普勒测速仪对有拦沙坝防护的模型桥墩附近流场进行了精细测量,对桥墩冲刷坑内三维流速分布进行了分析,给出了冲刷坑内三维紊动特征量的分布,分析研究了有拦沙防护坝时桥墩局部冲刷的三个新特点,提出了拦沙坝的适用条件。

第1/12页 1 2 3 4 5 6 7 8 9 ... > 尾页
推荐网络例句

We have no common name for a mime of Sophron or Xenarchus and a Socratic Conversation; and we should still be without one even if the imitation in the two instances were in trimeters or elegiacs or some other kind of verse--though it is the way with people to tack on 'poet' to the name of a metre, and talk of elegiac-poets and epic-poets, thinking that they call them poets not by reason of the imitative nature of their work, but indiscriminately by reason of the metre they write in.

索夫农 、森那库斯和苏格拉底式的对话采用的模仿没有一个公共的名称;三音步诗、挽歌体或其他类型的诗的模仿也没有——人们把&诗人&这一名词和格律名称结合到一起,称之为挽歌体诗人或者史诗诗人,他们被称为诗人,似乎只是因为遵守格律写作,而非他们作品的模仿本质。

The relationship between communicative competence and grammar teaching should be that of the ends and the means.

交际能力和语法的关系应该是目标与途径的关系。

This is not paper type of business,it's people business,with such huge money involved.

这不是纸上谈兵式的交易,这是人与人的业务,而且涉及金额巨大。