英语人>网络例句>主梁 相关的搜索结果
网络例句

主梁

与 主梁 相关的网络例句 [注:此内容来源于网络,仅供参考]

618 Method calculation on absolute maximum deflection on primary beam within bridge system composed of longitudinal and transverse beams

纵横梁桥面系统中主梁的跨度较长,纵梁上直接承受的车队荷载数量多且数值大,主梁设计中绝对最大挠度的确定是关键内容。

Taking the effect of non-radial bearings in the beam-ends into consideration, the rigid-crossbeam method was used to calculate the load lateral distribution of curved beam bridge with non-radial bearings as to get more accurate results.

用刚性横梁法计算非径向支承弯梁桥的荷载横向分布,在计算单梁挠度时考虑了主梁梁端非径向支承的影响,得到了更为精确的结果,根据影响参数,编制了相应的表格,方便工程设计人员查用。

This reflects that under the influence of dominant northwest wind, the primary ridges have the surface processes of transverse dunes.

副梁在主梁迎风坡上发育、侧向摆动和延伸,形成分、割主、副梁沉积的二级界面。

In this paper, Shenyang Fumin Bridge main girder to carry out innovative design of the traveling carriage, Based on the similar design of traveling carriage , adopted under the former anchor beam arc settings to resolve the fate of the plane rotation problem , makes the main truss rod assembly by universal application of the cradle of the space cable plane cable-stayed bridge girder construction.

摘 要:本文对沈阳市富民桥主梁的施工挂篮进行创新设计,参考同类挂篮的成功设计思路的基础上,通过将前锚梁下缘设置弧形来解决索的平面转动问题,使得主桁由万能杆件拼装的挂篮应用于空间索面的斜拉桥主梁施工中。

For the steel truss girder with abroad \\\"bridge crane bar assembled Law,\\\" the level of technology and equipment as a result of the limited duration of its long, far from being able to meet China\\\s bridge construction project as requested in the analysis of large-span suspension bridge mountain girder erection difficulties under the premise that after the election raised more than Aizhai Bridge \\\"self-cross-cable crane swing shift\\\" program to set up the main truss, which is mountainous suspension bridge girder erecting another major innovation.

对于钢桁梁,用国外的&桥面吊机杆件拼装法&,由于工艺和设备水平所限其工期长,远不能满足中国桥梁建设工期的要求,在分析山区大跨悬索桥主梁架设困难的前提下,经过多方案比选提出矮寨大桥&自行式跨缆吊机荡移&架设主桁方案,这是山区悬索桥主梁架设的又一个重大的创新。

The main, sub-beam handover, the first main beam arch camber, arch camber beam after the meeting.

主、次梁交接时,先主梁起拱,后次梁起拱。

Leung is a combination cable-stayed bridge for the main beam steel structure, the concrete structure of the bridge deck, the deck of the main beam and the combined force of the common cable-stayed bridge.

结合梁斜拉桥是一种主梁为钢结构,桥面系为混凝土结构,主梁与桥面系结合在一起共同受力的斜拉桥。

The entire Superstructure cross-section, except for traffic barrier, shall be considered to be placed at one time for purposes of determining support requirements and designing falsework girders for their stresses and deflections, except as follows: For concrete box girder bridges, the girder stems, diaphrams, crossbeams, and connected bottom slabs, if the stem wall is placed more than 5 days prior to the top slab, may be considered to be self supporting between falsework bents at the time the top slab is placed, provided that the distance between falsework bents does not exceed 4 times the depth of the portion of the girder placed in the preceding concrete placements.

整个上部结构截面除交通障碍,应被视为在一个确定的要求和支持他们的设计应力和挠度除,脚手架时间放在梁的目的如下:对于混凝土箱形梁桥,主梁茎,diaphrams,横梁,和连接底板,如果干墙放置超过5天前向顶板,可能被认为是自我支持之间的脚手架本茨当时顶端板放置,只要脚手架茨之间的距离不超过4倍,在前面的混凝土主梁部分存款放在深度。

The continous prestressed concrete girder bridge is divided into three inters,(30m+50m+30m), with the main span of 50m, and 30m-symmetry one.

本预应力混凝土连续梁桥共分为三跨(30m+50m+30m)主跨50m,边跨对称30m;主梁采用单箱单室预应力混凝土箱梁,跨中梁高为1.5m,支座处梁高为2.8m,截面高度按二次抛物线形式变化;桥面净宽为7+2×1.5m;设计荷载为公路-Ⅰ级。

For the structure stress condition, the dead load is born mainly by continuous rigid-frame, and the live load is born by both the arch rib and the main beam, the force separately bora by the arch rib and the main beam is influenced by the whole rigidity of beam and arch, and by areas of flexible hanger rod, the structure perforce is no longer same with the common beam and arch, and the inner force analysis progress is more complex to the common bridge system, especially, the multi-direction stress analysis to the combination area of pier、 arch and beam is very difficult, for such reasons, so it is very necessary and important to have stress performance analysis in the combination area of pier、 arch and beam.

从结构受力情况来看,梁体自重主要由连续刚构承受,活载由拱肋与主梁二者共同承受,各自承受力的大小受梁、拱相互整体刚度、柔性吊杆面积的大小影响,结构性能已不同于一般的拱与梁,结构内力分析的过程较一般桥梁体系较为复杂,特别是墩、拱、梁结合处的多向受力状况的分析难度更大,所以对该桥式结构,墩、拱、梁结合部的结构受力特性进行进一步地理论分析测验研究也就显得十分必要和迫切了。

第2/16页 首页 < 1 2 3 4 5 6 7 8 9 ... > 尾页
推荐网络例句

On the other hand, the more important thing is because the urban housing is a kind of heterogeneity products.

另一方面,更重要的是由于城市住房是一种异质性产品。

Climate histogram is the fall that collects place measure calm value, cent serves as cross axle for a few equal interval, the area that the frequency that the value appears according to place is accumulated and becomes will be determined inside each interval, discharge the graph that rise with post, also be called histogram.

气候直方图是将所收集的降水量测定值,分为几个相等的区间作为横轴,并将各区间内所测定值依所出现的次数累积而成的面积,用柱子排起来的图形,也叫做柱状图。

You rap, you know we are not so good at rapping, huh?

你唱吧,你也知道我们并不那么擅长说唱,对吧?