英语人>网络例句>下梁 相关的搜索结果
网络例句

下梁

与 下梁 相关的网络例句 [注:此内容来源于网络,仅供参考]

Eular -Bernonulli beam model and Tomosimko beam model were adapted to study the inherence vibration properties of the pipelines under dynamical loads, and the analytical answers of the chanmical results were brought out in the fifth chapter. And gave priority to the Eular -Bernonulli beam model, the simply and convenient analytical resolution for the response of the pipelines under dynamical traffic loads through the impulse function and the congruence method of the vibration form and so on.

本文采用Eular-Bernonulli梁模型和Tomosimko梁模型对动力下Kelvin粘弹性地基中管道固有振动性状进行了分析,提出了各力学结果描述的解析式;并以Eular-Bernonulli梁模型为主,基于脉冲函数、振型迭加法等对管道在动力交通荷载作用下的管道响应问题提出简单便捷的解析算法;在管道受力结果的分析中,考虑管道响应输出的随机性,将管道响应用随机过程来描述其概率特征,使得结果描述更加真实准确。

The formula is applied to designers. They can obtain the result of internal force under the condition of mutual action easily. The paper obtain more right calculative method , The result of the method is exacter than

为了解决这个问题,本文从梁板式阳台结构边梁与挑梁相互约束作用入手,对边梁与挑梁相互约束作用下结构内力的计算方法做了进一步的分析,指出节点性能对结构内力计算方法的影响。

In combination with the crushed rock slope as an example, the allocation of an anchorage force on longitudinal beams and transverse beams is calculated by adopting the distribution coefficient law of the nodal form at first. Then the internal forces of the lattice beam are calculated respectively through the software on the basis of Winkler elastic foundation model and the semi-infinite foundation model, and then compared with the internal forces which are based on simplified foundation pressure calculation. The active pressure of rock is calculated approximately by Ranking soil pressure theory in the working stage. Sequentially, the reinforcing bars are disposed by two-stage's averagely calculated values.

以破碎岩质边坡为例,采用节点荷载分配法计算了锚索锚固力在格构梁纵、横梁之间的分配比率,然后基于Winkler弹性地基模型和弹性半空间地基模型分别计算格构梁在张拉阶段的内力,并与采用简化的地基反力计算值对比;采用朗肯土压力理论近似计算在工作阶段主动岩体压力,将地梁视为在线性分布力作用下倒置于坡面上的连续梁,按力矩分配法计算地梁内力,取两阶段计算平均值进行配筋。

First, this paper presents three girders model with double cable planes which main girder and side girder is connected by rigid arms, analyzes the dynamic characteristic of Yonghe cable-stayed bridge and obtains its natural vibration modes (i.e., frequency, damping values and the mode shapes ) by ANLSIS structural analysis program and uses these parameters as dynamic dactylogram of the intact case of cable-stayed bridge. Using the passage of random as the ambient vibration ,the dynamic properties of Yonghe Bridge is measured and the modal parameter of its 15 years after is identified and used as dynamic dactylogram of the damaged case. By the finite element analysis and locale vibration test, damaged and undamaged modal parameter is analyzed and curvature mode shape, which is sensitive to damage state, is introduced as possible candidate for identifying and locating damage in the cable-stayed bridge. Selecting the branch of part measured point from modal parameter, this paper deduces the damaged index which can detect the possible damaged location of the cable-stayed bridge deck and identifies the damaged region and degree for Yonghe Bridge. For the purpose of structural condition monitoring in in-situ , from another viewpoint, this paper introduces the method called the best optimization vector to detect damaged location and degree. The accuracy and reliability of the method presented in this paper are demonstrated by static analysis and test and the healthy state of Yonghe Bridge can be evaluated.

建立了双索面通过刚臂与主梁及边梁相连的三梁式力学模型,采用ANSYS结构分析程序对永和斜拉桥进行动力分析,对其振动模态参数进行识别,以此作为斜拉桥完好状态下的动力&指纹&;采用自由交通流作为环境振源,对永和斜拉桥动力特性进行测试,识别出永和斜拉桥使用15年后的模态参数,确立了破损状态下的动力&指纹&;利用有限元分析、现场振动测试,对破损前后的模态参数进行分析,提取对破损状况较敏感的模态曲率作为斜拉桥破损诊断的参数;并从模态参数中选取部分点的分量,导出可以指示斜拉桥桥面大概损伤位置的Index损伤指标,识别出斜拉桥发生破损的区段及破损程度;考虑大型斜拉桥在线监测要求识别破损的具体位置,从另一角度提出采用最优矢量法具体确定破损发生的位置及程度;为验证本文研究成果,对永和斜拉桥进行静力分析及静力测试,对其健康状况提出可靠的评价。

In the end, Based on the conception that the simple beam at ultimate rotates rigidly around the plastic hinge in the midspan when the beam fails because of bending, the formula for calculating the stress in the external tendons and the ultimate anti-bending capacity of the beam in the cases of different deviators have been developed.

最后,基于抗弯承载力极限状态下的简支梁可视为梁体绕跨中等曲率塑性铰发生刚性转动的假设,推导了在各种转向块布置情况下求体外预应力筋的变形和梁的跨中挠度,进而求得梁的极限弯矩的简化公式。

For partially prestressed concrete I or T girder bridge,there is no sufficient stiffness owing to damage like prestress loss and cracks etc. The experiments of original and reinforced girders have been proved that the effect is remarkable to apply steel and concrete composite reinforcement method.

部分预应力混凝土I型或T型梁桥,由于预应力损失、裂缝损伤等造成主梁正常使用状态下刚度不足,采用钢-混凝土组合加固主梁,通过原梁及加固梁的加载试验,表明加固效果十分显著。

Through contrast analysis of stress value,the paper found warren box girder can improve prestress and precompression of prestress concrete box girder under border and box girder bearing capacity,reduce the distribution of prestress wire,saving construction quantity.

通过对同等条件的直腹箱梁和斜腹箱梁的应力值对比分析,提出将直腹箱梁改为斜腹箱梁后,可以提高预应力混凝土箱梁下缘的预压应力,提高箱梁承载力,降低预应力钢绞线的配置,节省工程数量。

At the same time, the finite staff element method is used to analyze the influence of beam rigidity; and the two new methods proposed are used to analyze the influence of connect way between piles and beam; and the conclusion is obtained that the rigidity ratio between beam and piles being 0.48 is appropriate; the continuative increase of the rigidity ratio is not significant; the worst condition is that connecting way between piles and beam is hinged; the best condition is that connecting way between piles and beam is rigid. Whether is single-row pile or are double-row piles, when the front of single-row pile or the front of the front-row pile(in the double-row piles) needed excavation, it is supposed to that ought to be carefulness to excavate, because it is that the engineering cost increased greatly.

同时,用有限杆单元法,对双排桩的连梁刚度和用文中提出的方法以桩梁连接方式进行了试验和理论分析得出如下结论:在满足不相互影响排桩间距的情况下,桩顶连梁与桩的刚度比不小于0.48是合适的,此时再增加连梁刚度无意义;桩梁连接为铰结时双排桩受力变形性质最差,刚结时受力变形性质最好;不论是单排桩还是双排桩,桩前和前排桩桩前土体需要开挖时应慎重,因为这种开挖对支护结构影响很大,造价增加很多;双排桩省钱,而且抵抗变形的能力强,值得在工程中研究和广泛应用

Finally, based on the theory of Timoshenko beam, a beam model of this crankshaft is built, which is compared with solid model. The results indicate that this beam model can meet the needs of calculation precision and calculation efficiency. With this beam model, the condition in which real loads are put on the crankshaft is simulated. The displacement curves、velocity curves、acceleration curves of the main journals and the pulley of this crankshaft and torsion vibration curve of the pulley are then gained. With these curves, the dynamic characteristic of the crankshaft is analyzed. The conclusion indicates that this crankshaft has good dynamic characteristic.

最后利用Timoshenko梁理论建立了曲轴的梁单元模型,将此梁单元模型与体单元模型进行了比较,结果表明梁单元模型能够满足精确度和计算效率的要求;利用该梁单元模型,模拟了实际条件下的载荷作用时曲轴的响应,得到了曲轴各主轴颈和皮带轮端的位移、速度、加速度曲线以及皮带轮端的扭转振动曲线,分析了曲轴的动态特性,结论表明该型曲轴具有良好的动态特性。

A three-span continuous curved box girder bridge model was made to meet the specific requirements of the research work of this paper.

制作了一个三跨混凝土曲线箱梁桥模型,基于合理的试验流程安排,进行多工况下的普通连续曲线箱梁桥和整体式桥台连续曲线箱梁桥的剪力滞效应试验,得到两种桥型在试验工况下的剪力滞系数。

第3/41页 首页 < 1 2 3 4 5 6 7 8 9 ... > 尾页
推荐网络例句

Finally, according to market conditions and market products this article paper analyzes the trends in the development of camera technology, and designs a color night vision camera.

最后根据市场情况和市面上产品的情况分析了摄像机技术的发展趋势,并设计了一款彩色夜视摄像机。

Only person height weeds and the fierce looks stone idles were there.

只有半人深的荒草和龇牙咧嘴的神像。

This dramatic range, steeper than the Himalayas, is the upturned rim of the eastern edge of Tibet, a plateau that has risen to 5 km in response to the slow but un stoppable collision of India with Asia that began about 55 million years ago and which continues unabated today.

这一引人注目的地域范围,比喜马拉雅山更加陡峭,是处于西藏东部边缘的朝上翻的边框地带。响应启始于约5500万年前的、缓慢的但却不可阻挡的印度与亚洲地壳板块碰撞,高原已上升至五千米,这种碰撞持续至今,毫无衰退。